# Manchester International Airport - Shotcrete works

[Kier Transportation - CP7 NWC](https://tendernation.io/buyers/kier-transportation-cp7-nwc)

Estimated value

£250,000 to £500,000

Published

6 Oct 2026

Deadline

Closed

16 Oct 2026

## Who can bid

- Buyer says suitable for SMEs

    The buyer ticked “suitable for SMEs” on the notice. Anyone can still bid.
- Open procedure

    Anyone can submit a full tender; there is no shortlisting stage.

[More contracts for small businesses and VCSEs](https://tendernation.io/opportunities/for-small-businesses)

## About this tender

The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable.Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport.

The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP):

A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services.

The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions.

The scope areas for this package are as follows:

-Preparation and cleaning of exposed contiguous piled retaining wall faces.

-Supply and installation of mesh reinforcement, anchor bars and injection mortar.

-Supply, delivery, application, curing and finishing of sprayed concrete (shotcrete).

-Formation and sealing of expansion and construction joints.

-Protection of adjacent assets from rebound, overspray and damage.

-Testing, inspection, quality assurance and handover documentation.

-Removal and disposal of rebound material, washout and associated waste.

-Working within a live rail and airport environment in accordance with all project and Network Rail requirements.

Read full description

## CPV classification

Ready-mixed concrete

Source

Contracts Finder (UK)

[View official notice](https://www.contractsfinder.service.gov.uk/notice/64a43aa2-d0e2-4988-9792-bdb6052db610)

Never miss a tender like this again

Get AI summaries, deadline alerts and a bid pipeline for tenders matched to your business. Free to start.

[Track tenders free](https://tendernation.io/register)

[Buyer profile Kier Transportation - CP7 NWC: past awards and live tenders](https://tendernation.io/buyers/kier-transportation-cp7-nwc) [Sector More Construction materials & structures tenders](https://tendernation.io/sectors/construction-materials)

## More tenders like this

[Manchester International Airport - Rail Footprint Civils · Kier Transportation - CP7 NWC · 2 days left · 22 Oct 2026](https://tendernation.io/opportunities/01a13f8a-8dbd-7332-84a4-dc3458cf785c/manchester-international-airport-rail-footprint-civils) [Manchester Piccadilly Strategic Regeneration Framework (SRF) Update · Manchester City Council · 2 days left · 21 Oct 2026](https://tendernation.io/opportunities/01a13bea-8abc-71e8-8f30-df1cf4a9d573/manchester-piccadilly-strategic-regeneration-framework-srf-update) [Heaton Reception Road Enhancement · Northern Trains Limited · 32 days left · 20 Nov 2026](https://tendernation.io/opportunities/01a145df-117d-72ed-82eb-fa982f8ae9fe/heaton-reception-road-enhancement)