# A303 Sparkford to Ilchester Surfacing

[galliford try](https://tendernation.io/buyers/galliford-try)

Estimated value

Not stated

Published

10 Mar 2020

Deadline

Closed

15 Mar 2021

## Who can bid

- Open procedure

    Anyone can submit a full tender; there is no shortlisting stage.

## About this tender

NOTIFICATION OF SURFACING SUBCONTRACT PACKAGE

### A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

### Package: Surfacing

We are seeking to appoint a Surfacing Contractor to support the development of the programme, methodology and target price. The successful bidder will also be appointed as Preferred Bidder for the Construction Stage (PCF6), and subject to the agreement of final target price, will deliver the Surfacing for the project without need for any further competition.

### Outline Scope of Works

The surfacing works involve the construction of approximately 100,000m2 of new main carriageway and associated interchanges and side roads. A Bill of Quantities is provided along with layout drawings. The majority of the new A303 dual carriageway sits to the north of the existing A303 however the new and existing carriageways cross at approx. ch3300 & ch3750 which will result in some temporary surfacing works.

### Programme

The construction programme is still under development. The initial surfacing works will involve the construction of Steat Hill Link and Downhead Junction Link with surfacing taking place in early 2021. The main carriageway surfacing is expected to take place during 2022. Tenderers should allow for 12 machine visits and 8 footpath / handlay visits. The surfacing works will be constructed within normal working hours with the exception of the tie ins and crossing points on the A303 which are likely to be undertaken during night time working. Extra Over costs for night time working should be clearly identified.

Bidders are invited to propose any areas of innovation that may offer benefits to the project including price, programme and quality and these will be taken into consideration when selecting the Preferred Bidder.

### Timings

Deadline for Notifications of Interest 17:30hrs Monday 16th March 2020

Deadline for tender submission 17:30hrs Monday 23rd March 2020

If this package is of interest to your company please contact the Managing QS \[Adrian Paddock\] by e-mail on , by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Additional information: NOTIFICATION OF SURFACING SUBCONTRACT PACKAGE

### A303 Sparkford to Ilchester

Galliford Try, as the South West Regional Delivery Partner are delivering the A303 Sparkford to Ilchester dualling project in the county of Somerset on behalf of Highways England. The project involves the design and construction of 5.6km of new dual lane all-purpose carriageway, connecting the existing dual carriageway at the Sparkford and Podimore Bypasses, therefore creating a continuous dual carriageway between Mere and the Podimore Roundabout.

The project is currently awaiting the approval of the Development Consent Order from the Secretary of State for Transport and this is expected to be given in early Spring 2020. Subject to receiving approval, the project is forecast to commence on site in late summer 2020 and will take around 2 years to complete.

### Package: Surfacing

We are seeking to appoint a Surfacing Contractor to support the development of the programme, methodology and target price. The successful bidder will also be appointed as Preferred Bidder for the Construction Stage (PCF6), and subject to the agreement of final target price, will deliver the Surfacing for the project without need for any further competition.

### Outline Scope of Works

The surfacing works involve the construction of approximately 100,000m2 of new main carriageway and associated interchanges and side roads. A Bill of Quantities is provided along with layout drawings. The majority of the new A303 dual carriageway sits to the north of the existing A303 however the new and existing carriageways cross at approx. ch3300 & ch3750 which will result in some temporary surfacing works.

### Programme

The construction programme is still under development. The initial surfacing works will involve the construction of Steat Hill Link and Downhead Junction Link with surfacing taking place in early 2021. The main carriageway surfacing is expected to take place during 2022. Tenderers should allow for 12 machine visits and 8 footpath / handlay visits. The surfacing works will be constructed within normal working hours with the exception of the tie ins and crossing points on the A303 which are likely to be undertaken during night time working. Extra Over costs for night time working should be clearly identified.

Bidders are invited to propose any areas of innovation that may offer benefits to the project including price, programme and quality and these will be taken into consideration when selecting the Preferred Bidder.

### Timings

Deadline for Notifications of Interest 17:30hrs Monday 16th March 2020

Deadline for tender submission 17:30hrs Monday 23rd March 2020

If this package is of interest to your company please contact the Managing QS \[Adrian Paddock\] by e-mail on , by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Read full description

## CPV classification

Road-surfacing machinery

Source

Contracts Finder (UK)

[View official notice](https://www.contractsfinder.service.gov.uk/notice/8d3a6832-cae0-4c29-8ff4-2e817560fa30)

Never miss a tender like this again

Get AI summaries, deadline alerts and a bid pipeline for tenders matched to your business. Free to start.

[Track tenders free](https://tendernation.io/register)

[Buyer profile galliford try: past awards and live tenders](https://tendernation.io/buyers/galliford-try) [Sector More Mining & construction machinery tenders](https://tendernation.io/sectors/mining-construction-machinery)

## More tenders like this

[Mobile hydraulic-powered mine roof supports – Dostawa zespołów i elementów wykonawczych sterujących hydrauliki sterowniczej do sekcji obudów zmechanizowanych dla Oddziałów Polskiej Grupy Górniczej S.A. - nr grupy 295-15. · Polska Grupa Górnicza S.A. · 39 days left · 27 Nov 2026](https://tendernation.io/opportunities/01a156a9-e755-719b-beec-8fc0dc6969a7/poland-mobile-hydraulic-powered-mine-roof-supports-dostawa-zespolow-i-elemen) [Mining equipment – Dostawa 4 lokomotyw dołowych akumulatorowych dla potrzeb PGG S.A. KWK Piast-Ziemowit Ruch Piast · Polska Grupa Górnicza S.A. · 37 days left · 25 Nov 2026](https://tendernation.io/opportunities/01a156aa-0d2f-7031-badb-643e6d08bc79/poland-mining-equipment-dostawa-4-lokomotyw-dolowych-akumulatorowych-dla-pot) [Parts of machinery for mining, quarrying and construction – REZERVNI DIJELOVI, POPRAVAK I SERVIS STROJEVA I PRIKLJUČNE OPREME ZA GRAĐEVINARSTVO · Zagrebački Holding d.o.o. · 29 days left · 17 Nov 2026](https://tendernation.io/opportunities/01a156a9-642d-70aa-89e8-1fff32455c6a/croatia-parts-of-machinery-for-mining-quarrying-and-construction-rezervni-d) [Irrigation equipment – Furnizare și montare sisteme fixe de irigații solarii Pepiniera Silvică Simileasca · Regia Nationala A Padurilor - Romsilva Ra · 30 days left · 18 Nov 2026](https://tendernation.io/opportunities/01a156a9-e6f9-7003-8bc4-419e9d4c21c0/romania-irrigation-equipment-furnizare-si-montare-sisteme-fixe-de-irigatii-s) [Sorting and screening machines – Sustitución de separador óptico para la mejora de eficiencia en la recuperación de envases de la fracción resto en la Planta de tratamiento de residuos de Cárcar (Navarra). · Servicios de Montejurra, S.A. · 32 days left · 20 Nov 2026](https://tendernation.io/opportunities/01a156aa-0ab1-71c4-adbd-46a9a788a50e/spain-sorting-and-screening-machines-sustitucion-de-separador-optico-para-la) [Irrigation equipment – Furnizare și montare sistem mobil de irigații Pepiniera Silvică Simileasca · Regia Nationala A Padurilor - Romsilva Ra · 30 days left · 18 Nov 2026](https://tendernation.io/opportunities/01a156aa-1b3e-7376-a755-e4eda31649e6/romania-irrigation-equipment-furnizare-si-montare-sistem-mobil-de-irigatii-p)