Source: https://tendernation.io/opportunities/01a13c34-a150-7216-991a-cfa151d4eabe/archictectural-riba-design-services-dublin

closed GB direct award procedure Suitable for SMEs

# Archictectural RIBA Design Services - Dublin

[FCO Services](https://tendernation.io/buyers/fco-services)

Estimated value

£1 to £118,000

Published

21 Dec 2018

Deadline

Closed

15 Feb 2019

## Who can bid

- Buyer says suitable for SMEs

    The buyer ticked “suitable for SMEs” on the notice. Anyone can still bid.
- Buyer says suitable for VCSEs

    The buyer ticked “suitable for voluntary, community and social enterprises” on the notice.

[More contracts for small businesses and VCSEs](https://tendernation.io/opportunities/for-small-businesses)

## About this tender

Consultants are invited to submit a fee proposal for a multi-disciplinary team to, design, tender and evaluate bids for the provision of:

- Residential building
- Boundary wall

A planning application was completed by O'Mahoney Pike Architects, DBFL engineers and serves as the basis point for developing a detailed design for tender and subsequent construction. The Option of building a new 3m high boundary wall & 5 bedroom residential building has been selected by the FCO to be developed into a tender package, to be delivered to the outline programme detailed in the following sections. The outline programme is to be developed further by the project team to take into account seasonal considerations, adjacent construction site works & security considerations.

Using the feasibility study as the basis, the design team is to review and further refine the proposed layout \[for agreement/ sign-off by the key stakeholders\] as part of RIBA Stage 2. This will include consideration to undertake minor amendments and update of the SOR to be agreed as part of a presentation before continuing to RIBA stage 3 & 4. As part of the stage 2 report, the design team is to comment on the construction strategy which will also take into account the adjacent construction site, to outline proposals for traffic management and security. The design team should note that these discussions will involve several senior stakeholders:

- British Ambassador to Dublin
- FCO Security Advisors
- MOD
- Irish Guarda
- Project team

The Stage 2 report should outline proposals for agreement and implementation in the next stages of the project.

The agreed design is to be developed to RIBA Stage 4 along with accompanying specifications, drawings, schedules and contract documents to tender the project under a RAIA form of contract, utilizing a design & build procurement route. To note, a task of the employer appointed QS (already engaged) will be to appraise various forms of contract and to recommend the appropriate form of contract to the FCO whilst liaising with the project team. The project team will be appointed by the project manager under a bespoke Professional Services Contract, with Collateral Warranties back to the FCO Services. The intention is that the design liability is novated to the D&B contractor once the construction contract is let, without prejudicing the CW's to the FCO.

The consultant will be required to work in conjunction with the client appointed QS to agree procurement packages, procurement routes and also to make sure the tender process conforms to the FCO standard, whilst utilizing the consultant's local construction knowledge. It is intended that the clients QS fulfils the contract administrator role, whilst the design team is novated to the principle contractor.

More details contained in Scope document.

Additional information:

Consultants are invited to submit a fee proposal for a multi-disciplinary team to, design, tender and evaluate bids for the provision of:

- Residential building
- Boundary wall

A planning application was completed by O'Mahoney Pike Architects, DBFL engineers and serves as the basis point for developing a detailed design for tender and subsequent construction. The Option of building a new 3m high boundary wall & 5 bedroom residential building has been selected by the FCO to be developed into a tender package, to be delivered to the outline programme detailed in the following sections. The outline programme is to be developed further by the project team to take into account seasonal considerations, adjacent construction site works & security considerations.

Using the feasibility study as the basis, the design team is to review and further refine the proposed layout \[for agreement/ sign-off by the key stakeholders\] as part of RIBA Stage 2. This will include consideration to undertake minor amendments and update of the SOR to be agreed as part of a presentation before continuing to RIBA stage 3 & 4. As part of the stage 2 report, the design team is to comment on the construction strategy which will also take into account the adjacent construction site, to outline proposals for traffic management and security. The design team should note that these discussions will involve several senior stakeholders:

- British Ambassador to Dublin
- FCO Security Advisors
- MOD
- Irish Guarda
- Project team

The Stage 2 report should outline proposals for agreement and implementation in the next stages of the project.

The agreed design is to be developed to RIBA Stage 4 along with accompanying specifications, drawings, schedules and contract documents to tender the project under a RAIA form of contract, utilizing a design & build procurement route. To note, a task of the employer appointed QS (already engaged) will be to appraise various forms of contract and to recommend the appropriate form of contract to the FCO whilst liaising with the project team. The project team will be appointed by the project manager under a bespoke Professional Services Contract, with Collateral Warranties back to the FCO Services. The intention is that the design liability is novated to the D&B contractor once the construction contract is let, without prejudicing the CW's to the FCO.

The consultant will be required to work in conjunction with the client appointed QS to agree procurement packages, procurement routes and also to make sure the tender process conforms to the FCO standard, whilst utilizing the consultant's local construction knowledge. It is intended that the clients QS fulfils the contract administrator role, whilst the design team is novated to the principle contractor.

More details contained in Scope document.

Read full description

## CPV classification

Architectural design services

Source

Contracts Finder (UK)

[View official notice](https://www.contractsfinder.service.gov.uk/notice/11dafdc7-4be2-4ed4-80a1-6db29c8f9af6)

Never miss a tender like this again

Get AI summaries, deadline alerts and a bid pipeline for tenders matched to your business. Free to start.

[Track tenders free](https://tendernation.io/register)

[Buyer profile FCO Services: past awards and live tenders](https://tendernation.io/buyers/fco-services) [Sector More Architecture, engineering & surveying tenders](https://tendernation.io/sectors/architecture-engineering-surveying)

## More tenders like this

[Asbestos Management Framework · Home Group · 25 days left · 13 Nov 2026](https://tendernation.io/opportunities/01a15476-5fff-736e-ae2e-0c8a400c7297/asbestos-management-framework) [Infrastructure works consultancy services – Contrôle extérieur des chaussées · Collectivité européenne d Alsace · 29 days left · 17 Nov 2026](https://tendernation.io/opportunities/01a15183-1730-733b-8247-a32bbbe2211c/france-infrastructure-works-consultancy-services-controle-exterieur-des-chau) [Architectural, construction, engineering and inspection services – Single Party Framework Agreement for Architect Led Integrated Design Team Services for Fire Safety Remediation Works for Dublin City Council · Dublin City Council · 5 days left · 23 Oct 2026](https://tendernation.io/opportunities/01a15183-0a15-7156-849b-5a223dd6d615/ireland-architectural-construction-engineering-and-inspection-services-sin) [Architectural, construction, engineering and inspection services – Būvprojekta izstrāde un autoruzraudzība fasādes siltināšanai kārtās Dzirciema ielā 16, Rīgā – 1.kārta, C korpuss · Rīgas Stradiņa universitāte · 28 days left · 16 Nov 2026](https://tendernation.io/opportunities/01a15183-3915-73d1-83e6-c378f9f7a926/latvia-architectural-construction-engineering-and-inspection-services-buvp) [Technical assistance services – Suivi et gestion de chantiers de réhabilitation de sites pollués · SPAQuE · 15 days left · 3 Nov 2026](https://tendernation.io/opportunities/01a15183-155e-73c2-a593-9e17375422ac/belgium-technical-assistance-services-suivi-et-gestion-de-chantiers-de-rehab) [Engineering design services for the construction of civil engineering works – Dokumentace pro povolení záměru stavby č. 9567 Radlická radiála JZM - Smíchov; v úseku MÚK Bucharova – MÚK Jinonice · Hlavní Město Praha · 15 days left · 3 Nov 2026](https://tendernation.io/opportunities/01a15183-0c15-72b2-bb19-c3ab1550e67e/czechia-engineering-design-services-for-the-construction-of-civil-engineering)